Which of the following statements regarding construction of Rohtang tunnel is NOT correct ?
Show answer & solutionHide answer & solution
Option A
Why
The Rohtang tunnel under the Pir Panjal range is at about 3,000 m, or 10,000 feet, not 5,000 feet. As of the exam it was being built by the Border Roads Organisation. It was renamed the Atal Tunnel and opened in October 2020.
Exam-hall approach
Manali itself is at about 2,000 m (6,700 feet). A tunnel above Manali, beside the Rohtang Pass, cannot be at 5,000 feet.
Proof
Border Roads Organisation: Rohtang tunnel, under construction at about 3,000 m (10,000 ft), 8.8 km long, shortening the Manali–Leh road by about 46 km, as of 2018-04-22
About the other options
Option B
Correct: it gives all-weather access to Lahaul and Spiti, which the Rohtang Pass cuts off in winter.
Option C
Correct: the Border Roads Organisation built the tunnel.
Option D
Correct: it shortens the Manali–Leh road by about 46 km, close to 50 km.