Technique
Time and work: call the whole job the LCM of the days, in units
Quantitative Aptitude • Time and Work
Statement
If A takes a days and B takes b days for the whole job, call the job LCM(a, b) units. A then does LCM a units a day and B does LCM b. Working together, the units per day add. Work done = units per day days, and work left = total work done. This avoids adding fractions.
How to use it
- 1Find each worker's days for the whole job; for example, a third in 6 days means the whole in 18.
- 2Take the job as the LCM of these days, in units.
- 3Units per day = total units days for each worker; add for workers together.
- 4Use units done = units per day days to fill in the missing part.
Worked example
A can do a job in 10 days and B in 15 days. They work together for 3 days, and then B finishes alone. How many more days does B take?
Step-by-step
- 1Job = LCM(10, 15) = 30 units. A does 3 a day, B does 2 a day.
- 2Together for 3 days: units.
- 3Left: units; B alone: days.
Why: Only B is working now.
Answer
7.5 days.
Watch out
Adding the days instead of the daily work is the classic trap. Also, a part done in some days must first be turned into the whole job's days.