Formula

The work-equivalence chain rule

Arithmetic • Time and Work

Formula

If workers of equal efficiency take days of hours each to finish a job, the product measures the job and is the same for any other workforce doing the same job: . With efficiencies differing between groups, the invariant is .

How to use it

  1. 1Compute the job once as a total in man-hours, then divide by the new daily output to get the new number of days.
  2. 2When two kinds of worker are mixed, first convert one into the other using the stated exchange rate (e.g. women men, so one woman is of a man).
  3. 3Drop when the working day is not mentioned; the rule then reads .

Worked example

If men take days of hours each to build a wall, how many days of hours each will men take?

Step-by-step

  1. 1
    man-hours

    Why: Measure the whole job in man-hours.

  2. 2

    Why: The same job, done by the new workforce.

  3. 3

Answer

days

Watch out

It assumes every worker in a group is equally efficient and that output scales linearly. Convert mixed workforces to a single unit BEFORE multiplying, and never add men to women directly.

Builds on

Also known as

men days hours, work equivalence, chain rule of work, man-hours, M1D1H1 = M2D2H2, men and women work ratio