Formula
The work-equivalence chain rule
Arithmetic • Time and Work
Formula
If workers of equal efficiency take days of hours each to finish a job, the product measures the job and is the same for any other workforce doing the same job: . With efficiencies differing between groups, the invariant is .
How to use it
- 1Compute the job once as a total in man-hours, then divide by the new daily output to get the new number of days.
- 2When two kinds of worker are mixed, first convert one into the other using the stated exchange rate (e.g. women men, so one woman is of a man).
- 3Drop when the working day is not mentioned; the rule then reads .
Worked example
If men take days of hours each to build a wall, how many days of hours each will men take?
Step-by-step
- 1man-hours
Why: Measure the whole job in man-hours.
- 2
Why: The same job, done by the new workforce.
- 3
Answer
days
Watch out
It assumes every worker in a group is equally efficient and that output scales linearly. Convert mixed workforces to a single unit BEFORE multiplying, and never add men to women directly.